PMP practice question 22 of 35
A few developers have identified a list of impediments at the daily standup and are asking for the project lead's assistance in prioritizing them…
Choose your answer, then check it against the explanation.
Domain People
A few developers have identified a list of impediments at the daily standup and are asking for the
project lead's assistance in prioritizing them. There are a few complex backlog items, and a new
junior tester has identified a few compliance defects. The product owner and a couple of developers
will be leaving the project team, and the contract with the test and production support partner will
not be renewed.
Which issue should the project lead focus on first?
Question 22 of 35
Keep practicing
Take the free PMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMP practice questions
- Question 1In a daily standup meeting, a project manager notices that a team member's reports includ…
- Question 2In a geographically distributed team, a developer continues to delay a coding activity. T…
- Question 3A project manager has an engineering team mostly comprised of new hires. The project mana…
- Question 5A project manager is part of an organization that is assessing the use of agile delivery …
- Question 6A project team is using a vendor solution. The project team has been notified that the ve…
- Question 7During the initial stage of a project, the team estimated activities for the next iterati…
