AACE-INTERNATIONAL-PSP practice question 26 of 30
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?
Full set: 211 questionsWhen a change order increases the duration of Activity 6001, two primary types of activities are affected in the schedule update. First, the data for Activity 6001 itself must be changed (i.e., its duration is increased). Second, if Activity 1000 represents a summary activity for the entire project or a Level of Effort (LOE) activity whose duration is linked to the project's start and finish dates, its duration will also change to reflect the new, longer project completion date caused by the delay to Activity 6001. This is a common scheduling practice for representing overall project management or overhead activities.
A. This option is incomplete as it omits the impact on the overall project summary or LOE activity (1000).
B. The project start milestone (a likely role for an early activity like 1000 or 1001) would not change, as the project has already progressed.
C. This option incorrectly omits Activity 6001, which is the source of the change and must be updated.
1. AACE International
Skills & Knowledge of Cost Engineering
6th Edition
(2015)
Section 2.3.3.3
p. 153. Discusses schedule maintenance and updates
stating that changes in scope or duration require modifying the schedule logic and recalculating dates.
2. AACE International
Recommended Practice No. 10S-90
Cost Engineering Terminology
(June 20
2019)
Page 66. Defines "Level of Effort (LOE)" as "Activity that is not readily measured by a discrete accomplishment... Its duration is determined by its dependent activities." A change to a dependent activity would change the LOE duration.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …