AACE-INTERNATIONAL-PSP practice question 28 of 30
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?
Full set: 211 questionsA non-excusable delay is a delay attributable to the contractor's own fault, negligence, or inaction. For such delays, the contractor is not entitled to any relief from the owner. The contractor must absorb the costs associated with the delay and is responsible for the time impact, potentially facing liquidated damages for late completion. Therefore, this type of delay results in neither a time extension nor additional compensation.
B. Compensable delay: This is an excusable delay for which the contractor is entitled to both a time extension and additional compensation from the owner.
C. Non-compensable delay: This is an excusable delay for which the contractor is entitled to a time extension but not additional compensation (e.g., force majeure).
D. Excusable delay: This is a broad category that includes both compensable and non-compensable delays, both of which grant a time extension to the contractor.
1. AACE International Recommended Practice No. 29R-03
"Forensic Schedule Analysis
" (April 25
2011). Section 1.4.C.2 defines Non-Excusable Delay as being caused by the contractor
who "is not entitled to a time extension or delay damages."
2. AACE International
Skills and Knowledge of Cost Engineering
6th Ed.
Morgantown
WV: AACE International
2015. Chapter 37 (Managing Claims and Disputes) discusses the different categories of delay and their entitlement consequences
aligning with this answer.
3. Cala
C. M.
& Pointner
P. (2015). AACE International's Certified Estimating Professional (CEP) Certification Study Guide
2nd Ed. AACE International. Chapter 10 discusses contract terms and delay types
clarifying that non-excusable delays offer no relief to the contractor.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …