AACE-INTERNATIONAL-PSP practice question 28 of 30

Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

Full set: 211 questions
Answer options
A: Non-excusable delay Correct answer
B: Compensable delay
C: Non-compensable delay
D: Excusable delay
Correct Answer:
A. Non-excusable delay
Explanation

A non-excusable delay is a delay attributable to the contractor's own fault, negligence, or inaction. For such delays, the contractor is not entitled to any relief from the owner. The contractor must absorb the costs associated with the delay and is responsible for the time impact, potentially facing liquidated damages for late completion. Therefore, this type of delay results in neither a time extension nor additional compensation.

Why Incorrect

B. Compensable delay: This is an excusable delay for which the contractor is entitled to both a time extension and additional compensation from the owner.
C. Non-compensable delay: This is an excusable delay for which the contractor is entitled to a time extension but not additional compensation (e.g., force majeure).
D. Excusable delay: This is a broad category that includes both compensable and non-compensable delays, both of which grant a time extension to the contractor.

References

1. AACE International Recommended Practice No. 29R-03

"Forensic Schedule Analysis

" (April 25

2011). Section 1.4.C.2 defines Non-Excusable Delay as being caused by the contractor

who "is not entitled to a time extension or delay damages."

2. AACE International

Skills and Knowledge of Cost Engineering

6th Ed.

Morgantown

WV: AACE International

2015. Chapter 37 (Managing Claims and Disputes) discusses the different categories of delay and their entitlement consequences

aligning with this answer.

3. Cala

C. M.

& Pointner

P. (2015). AACE International's Certified Estimating Professional (CEP) Certification Study Guide

2nd Ed. AACE International. Chapter 10 discusses contract terms and delay types

clarifying that non-excusable delays offer no relief to the contractor.