PMI-SP practice question 18 of 35
You are the project manager of the MQQ project. Unfortunately, this project is not performing well and you must do something to address the problems…
Full set: 327 questionsChange requests are an output of performance report, and allow the project manager to address corrective actions and preventive actions to help the project get back in alignment with performance baselines. Answer option B is incorrect. While performance reports are an output of the performance reporting, these reports do not specifically address the problems in the project. Answer option A is incorrect. Updating the organizational process assets is an important activity, but it does not address the poor performance directly. Answer option C is incorrect. Performance re-baselining is not an output of performance reporting so this choice is not valid.
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…
