AACE-INTERNATIONAL-PSP practice question 17 of 30
What method offers the best chance of the schedule being used effectively to implement the project in the field?
Full set: 211 questionsFor a schedule to be an effective management tool in the field, it must be accepted and owned by the team responsible for executing the work. Obtaining consent and agreement from key project personnel (e.g., superintendents, foremen, subcontractors) ensures their buy-in. This collaborative approach makes the schedule more realistic and transforms it from a mere contractual requirement into a practical guide for day-to-day operations. Team members who help build the plan are more likely to be committed to following it, communicating deviations, and using it to proactively manage the work. This ownership is the most critical factor for effective implementation.
A. Excessively frequent or detailed updates can be overwhelming and impractical for field personnel, leading them to ignore the schedule altogether.
C. Stringent specifications can create an adversarial environment, where the schedule is seen as a compliance tool rather than a management aid.
D. Large time contingencies obscure the critical path and can encourage inefficiency (Parkinson's Law), making the schedule less useful for managing priorities.
1. AACE International. (2015). Total Cost Management Framework: An Integrated Approach to Portfolio, Program, and Project Management (2nd ed.). Section 7.3 – Schedule Planning and Development. (Emphasizes the schedule as a communication tool and the need for team commitment).
2. AACE International. (2016). Recommended Practice No. 39R-06: Project Planning and Scheduling. AACE International. Section 1.3 – Purpose. (Highlights the schedule as a tool for communication and consensus).
3. Cioffi, D. F. (2006). The Importance of Project Sponsorship in Creating Project Success. Cost Engineering, 48(10), 24-30. (Discusses the importance of buy-in and commitment from stakeholders for project success).
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …