AACE-INTERNATIONAL-PSP practice question 17 of 30

What method offers the best chance of the schedule being used effectively to implement the project in the field?

Full set: 211 questions
Answer options
A: Issue detailed schedule updates as frequently as possible.
B: Obtain consent and agreement to the schedule from the key project personnel. Correct answer
C: Include detailed and stringent set of scheduling specifications in the contract.
D: Allow large time contingencies on milestones and completion deadlines.
Correct Answer:
B. Obtain consent and agreement to the schedule from the key project personnel.
Explanation

For a schedule to be an effective management tool in the field, it must be accepted and owned by the team responsible for executing the work. Obtaining consent and agreement from key project personnel (e.g., superintendents, foremen, subcontractors) ensures their buy-in. This collaborative approach makes the schedule more realistic and transforms it from a mere contractual requirement into a practical guide for day-to-day operations. Team members who help build the plan are more likely to be committed to following it, communicating deviations, and using it to proactively manage the work. This ownership is the most critical factor for effective implementation.

Why Incorrect

A. Excessively frequent or detailed updates can be overwhelming and impractical for field personnel, leading them to ignore the schedule altogether.
C. Stringent specifications can create an adversarial environment, where the schedule is seen as a compliance tool rather than a management aid.
D. Large time contingencies obscure the critical path and can encourage inefficiency (Parkinson's Law), making the schedule less useful for managing priorities.

References

1. AACE International. (2015). Total Cost Management Framework: An Integrated Approach to Portfolio, Program, and Project Management (2nd ed.). Section 7.3 – Schedule Planning and Development. (Emphasizes the schedule as a communication tool and the need for team commitment).

2. AACE International. (2016). Recommended Practice No. 39R-06: Project Planning and Scheduling. AACE International. Section 1.3 – Purpose. (Highlights the schedule as a tool for communication and consensus).

3. Cioffi, D. F. (2006). The Importance of Project Sponsorship in Creating Project Success. Cost Engineering, 48(10), 24-30. (Discusses the importance of buy-in and commitment from stakeholders for project success).