AACE-INTERNATIONAL-PSP practice question 18 of 30
Schedules are periodically updated to reflect progress. What step should NOT occur before the update is considered complete?
Full set: 211 questionsA critical part of completing a schedule update is to analyze the results of the new data. This includes identifying the current critical path, as it may have shifted due to variances in progress. Revisiting the critical path and near-critical paths is essential to understand the project's current risk profile and to validate that the remaining logic and durations are still accurate for forecasting completion. Therefore, not revisiting the critical path is an incorrect action and should not be part of a proper update process.
A. Reviewing contiguous activities helps ensure the logic of the reported progress is sound and is a good practice during an update.
B. The responsible manager providing status is the primary source of progress data and a fundamental step in the update process.
D. A final review of the statused schedule by the project team is a crucial quality control step to ensure accuracy before finalizing the update.
1. AACE International
Recommended Practice No. 23R-02
"Identification of the Critical Path and Near-Critical Paths of a Schedule
" (April 29
2019)
Section 1.3
p. 2.
2. Stephenson
H. L.
AACE International's Planning and Scheduling Certification Study Guide
2nd Ed.
(Morgantown
WV: AACE International
2016)
Chapter 10: Schedule Maintenance and Control
pp. 10-1 to 10-3.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …