AACE-INTERNATIONAL-PSP practice question 19 of 30
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using
Full set: 211 questionsTo create a condition where project slippage results in negative float, a "Finish-No-Later-Than" (FNLT) constraint must be applied to the final activity or project milestone. This constraint imposes a hard deadline. The scheduling software uses this date as the starting point for the backward pass calculation to determine late dates. If the forward pass calculation results in an early finish date that is later than this constrained late finish date, the total float (Late Finish - Early Finish) becomes negative, indicating a schedule overrun against the deadline.
A: A finish-no-earlier constraint on the first activity would only delay the project's start; it would not create a cap on the end date. B: A finish-no-earlier constraint on the last activity sets a target to finish after, not a deadline to finish before, and would not generate negative float. D: A start-no-later constraint on the first activity restricts the project start but does not directly control the project's overall completion deadline.
1. AACE International
Recommended Practice No. 29R-03
"Forensic Schedule Analysis
" (April 25
2011)
Section 1.4.C.3
p. 14. Discusses constraints and their effect on float calculations
noting that late constraints can result in negative float.
2. AACE International
Recommended Practice No. 10S-90
"Cost Engineering Terminology
" (June 18
2019)
p. 82. Defines "Negative Float" as occurring when the "late start or finish date is earlier than the early start or finish date
" a condition created by a late constraint.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …
