AACE-INTERNATIONAL-PSP practice question 20 of 30
Time-scaled logic diagrams are
Full set: 211 questionsA time-scaled logic diagram is a project schedule network diagram where the horizontal axis represents a calendar timeline. Activities are drawn as bars with their length proportional to their duration, and their placement along the axis corresponds to their calculated start and finish dates. This format combines the logical dependencies of a pure-logic diagram with the intuitive time-based visualization of a Gantt chart. It clearly shows the timing of activities, their logical ties, and the amount of float (often shown as a flexible line or different bar type) in relation to the calendar.
A. While computers greatly facilitate their creation, time-scaled diagrams can be, and historically were, drawn manually.
B. A pure-logic diagram shows only relationships; the length and position of lines have no temporal meaning. A time-scaled diagram is drawn to a calendar scale.
C. Calculating the most probable duration is a feature of estimation techniques like PERT, not a characteristic of how a logic diagram is drawn.
1. AACE International. (2016). Recommended Practice No. 10S-90: Cost Engineering Terminology. Defines "Logic Diagram, Time-Scaled" as "A logic diagram with a horizontal time scale. The activity symbols are plotted on the diagram at the time they are scheduled to occur." (p. 68).
2. East, E. W. (2016). Critical Path Method (CPM) Tutor for Construction Planning and Scheduling. University of Illinois at Urbana-Champaign. Chapter 3, "Schedule Visualization," distinguishes between pure logic diagrams and time-scaled network diagrams, noting the latter are "drawn so that the position of the activity reflects its schedule dates."
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …