AACE-INTERNATIONAL-PSP practice question 21 of 30
How could the structural steel drawing delay have been prevented?
Full set: 211 questionsDelays in the submittal and review process for critical items like structural steel drawings are a common and foreseeable project risk. The most effective preventative measure is proactive planning. By incorporating realistic durations for the initial review, potential revisions, and subsequent resubmittals into the baseline schedule, the project plan accurately reflects the time this iterative process requires. This prevents the review cycle from consuming float and becoming a source of delay, as the necessary time is already accounted for in the project's critical path.
A. Adding a buffer is a contingency for a delay, not a method to prevent the process from taking too long in the first place.
C. This is a high-risk schedule compression tactic (fast-tracking) that can lead to significant rework and cost if drawings are not approved.
D. This is a complete design change that avoids the problem rather than managing the original risk within the planned scope.
1. AACE International
Recommended Practice No. 39R-03
Project Planning – As Applied in Engineering and Construction for Capital Projects
Section 3.3.2
2008. (This section emphasizes that the project plan must define the review and approval requirements for deliverables like drawings).
2. AACE International. (2015). AACE International's Skills & Knowledge of Cost Engineering (6th ed.). AACE International. Chapter 9 (Project Scheduling)
Section 9.2 discusses the importance of including non-construction activities like submittals and approvals in the schedule logic.
3. Hinze
J. W. (2008). Construction Planning and Scheduling (3rd ed.). Pearson. Chapter 5 emphasizes the need to schedule administrative procedures
including shop drawing review and approval
as distinct activities with realistic durations.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …