AACE-INTERNATIONAL-PSP practice question 22 of 30

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project…

Full set: 211 questions
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
Answer options
A: Not suitable for complicated projects with multiple planned critical paths.
B: Accuracy is increased by inserting delaying events into the as-planned schedule. Correct answer
C: Not suitable for projects with long durations.
D: Less accurate as the analysis advances through the project.
Correct Answer:
B. Accuracy is increased by inserting delaying events into the as-planned schedule.
Explanation

A simple As-Planned vs. As-Built (APAB) analysis is a static, observational method that compares the planned schedule with the final as-built record. It does not involve modeling or inserting delay events into the as-planned schedule to determine their impact. The action described—inserting delaying events into a schedule—is characteristic of a more sophisticated, dynamic analysis methodology, such as a Time Impact Analysis (TIA) or a modeled analysis. Therefore, this statement does not apply to a simple APAB.

Why Incorrect

A. APAB is ill-suited for complex projects because it cannot effectively model or explain shifts in the critical path.
C. On long projects, the original as-planned schedule becomes outdated and an unrealistic baseline for comparison, reducing the validity of an APAB.
D. The APAB method's accuracy diminishes over time as the project deviates further from the original plan, making causation difficult to establish.

References

1. AACE International

Recommended Practice No. 29R-03

Forensic Schedule Analysis

(Rev. April 25

2011)

Section 3.2. This RP describes the APAB method as a static comparison and contrasts it with dynamic

modeled methods (like TIA) where delays are inserted into a network model.

2. Winter

R. M. (2017). AACE International's Professional Practice Guide to Forensic Scheduling. AACE International. Chapter 5 discusses various delay analysis methods

clearly distinguishing the simple comparative nature of APAB from the simulative approach of a TIA.

3. Keane

P. J.

& Caletka

A. F. (2015). Delay and Disruption in Construction Contracts (5th ed.). Wiley-Blackwell. Chapter 11 outlines the limitations of simplistic "as-planned vs. as-built" methods in complex scenarios.