AACE-INTERNATIONAL-PSP practice question 22 of 30
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project…
Full set: 211 questionsA simple As-Planned vs. As-Built (APAB) analysis is a static, observational method that compares the planned schedule with the final as-built record. It does not involve modeling or inserting delay events into the as-planned schedule to determine their impact. The action described—inserting delaying events into a schedule—is characteristic of a more sophisticated, dynamic analysis methodology, such as a Time Impact Analysis (TIA) or a modeled analysis. Therefore, this statement does not apply to a simple APAB.
A. APAB is ill-suited for complex projects because it cannot effectively model or explain shifts in the critical path.
C. On long projects, the original as-planned schedule becomes outdated and an unrealistic baseline for comparison, reducing the validity of an APAB.
D. The APAB method's accuracy diminishes over time as the project deviates further from the original plan, making causation difficult to establish.
1. AACE International
Recommended Practice No. 29R-03
Forensic Schedule Analysis
(Rev. April 25
2011)
Section 3.2. This RP describes the APAB method as a static comparison and contrasts it with dynamic
modeled methods (like TIA) where delays are inserted into a network model.
2. Winter
R. M. (2017). AACE International's Professional Practice Guide to Forensic Scheduling. AACE International. Chapter 5 discusses various delay analysis methods
clearly distinguishing the simple comparative nature of APAB from the simulative approach of a TIA.
3. Keane
P. J.
& Caletka
A. F. (2015). Delay and Disruption in Construction Contracts (5th ed.). Wiley-Blackwell. Chapter 11 outlines the limitations of simplistic "as-planned vs. as-built" methods in complex scenarios.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …