AACE-INTERNATIONAL-PSP practice question 23 of 30
Assumptions made during the planning stage should be_____________.
Full set: 211 questionsAssumptions are necessary placeholders for unknown information during the initial planning stages. They are foundational to creating the initial project plan and schedule. However, a core principle of progressive elaboration and effective project management is to actively seek out factual information to replace these assumptions as the project moves forward. This reduces uncertainty and risk, leading to a more accurate and reliable plan. Leaving assumptions unverified increases the risk of project failure.
A. While assumptions are a source of risk, the primary goal is to eliminate them with facts, not simply to shift the risk.
C. Experience is a valid basis for assumptions, but stating it as the sole basis is too restrictive; other sources are also used.
D. Assumptions must be documented, but specifying an "internal memo" is arbitrary; they are typically recorded in a Basis of Schedule or project plan.
1. AACE International. (2019). Recommended Practice No. 10S-90: Cost Engineering Terminology. Document ID 15834, p. 13. (Defines "Assumption" as a statement taken as true in the absence of proof for the purpose of planning).
2. AACE International. (2015). Skills & Knowledge of Cost Engineering (6th ed.). Section 2.2.2, p. 2.2.5. (Discusses the planning process, which involves making assumptions that are refined as more information becomes available).
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …
