AACE-INTERNATIONAL-PSP practice question 24 of 30
Which is NOT an industry-recognized methodology for quantifying critical delay?
Full set: 211 questionsA Gantt Chart is a graphical representation of a schedule, typically in the form of a bar chart. While it displays the output of a schedule analysis, it is not, in itself, a methodology for quantifying delay. Recognized forensic delay analysis methodologies, such as Time Impact Analysis, Windows Analysis, or Collapsed As-Built, are analytical processes that use the underlying schedule logic (e.g., the Critical Path Method network) to determine the cause and extent of delays. These methods produce results that can be displayed on a Gantt chart, but the chart is the visualization tool, not the analytical method.
B. Periodic Windows (or Windows Analysis) is a recognized forensic schedule analysis methodology (AACE RP 29R-03, MIP 3.7) that analyzes delay in discrete time periods.
C. Collapsed As-Built is a recognized subtractive, retrospective forensic schedule analysis methodology (AACE RP 29R-03, MIP 3.9).
D. Time Impact Analysis (TIA) is a recognized prospective, additive forensic schedule analysis methodology (AACE RP 29R-03, MIP 3.6).
1. AACE International. (2011). Recommended Practice No. 29R-03: Forensic Schedule Analysis. Section 3
"Method Implementation Protocols
" pp. 19-106. This document details the various accepted methodologies
including Time Impact (MIP 3.6)
Windows (MIP 3.7)
and Collapsed As-Built (MIP 3.9)
but does not list Gantt Chart as an analytical method.
2. Hegazy
T. (2002). Computer-Based Construction Project Management. University of Waterloo. Chapter 5
"Project Time Management
" describes Gantt charts as a tool for "illustrating the project schedule" and not as a delay analysis technique.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …